自然资源学报 ›› 2005, Vol. 20 ›› Issue (1): 1-6.doi: 10.11849/zrzyxb.2005.01.001

• 资源利用与管理 •    下一篇

塔里木河下游第五次应急输水后地下水恢复量的计算

杨鹏年1, 董新光1, 吾买尔江2   

  1. 1. 新疆农业疆学水利与土木工程学院, 乌鲁木齐 830052;
    2. 塔里木河流域管理局, 新疆库尔勒 841000
  • 收稿日期:2004-05-19 修回日期:2004-08-19 出版日期:2005-02-25 发布日期:2005-02-25
  • 通讯作者: 董新光,教授,博士生导师.E-mail:Dong@xj.cninfo.net E-mail:Dong@xj.cninfo.net
  • 作者简介:杨鹏午(1966-),男.甘肃武威人.博士生.主要从事地下水资源研究.
  • 基金资助:

    水利部科技创新项目(SCX2001_02)资助.

Calculation of Groundwater Recharge Volume after the Fifth Emergency Water Transfer to the Lower Reaches of the Tarim River, Xinjiang

YANG Peng-nian1, DONG Xin-guang1, Omerjan2   

  1. 1. College of Water Conservancy and Civil Engineering, Xinjang Agriculture Unversity, Urumqi 830052, China;
    2. Management Bureau of Tarim River Basin, Korla 841000, China
  • Received:2004-05-19 Revised:2004-08-19 Online:2005-02-25 Published:2005-02-25

摘要: 依据塔里木河下游应急输水前与第五次第一阶段输水后地下水的监测资料,分析了输水前后地下水位的响应特征:地下水位在应急输水前持续下降,呈近似水平状态;输水后则由于接受了河道渗漏的补给,地下水位表现出逐次回升的趋势且受输水的影响,宽度(距离河道)也随之加大。在此基础上,逐断面拟合了第五(I)次输水后地下水位与离河距离的二次多项式方程,同时运用地下水水均衡的原理,推导了计算地下水净恢复量的数学公式,并以此为工具对第五(I)次输水后地下水的净恢复量进行了计算。

关键词: 间歇输水, 地下水位, 恢复量, 塔里木河下游

Abstract: Tarim River is the longest inland river in China.It is located at the north of the Tarim Basin.However,the river flow in the 357-km-long section of the lower reaches had been cut off since 1972.The groundwater level had declined from 2.9~7.0m to 8.1~12.9m.In order to protect the eco-environment and save the existing vegetation in the lower Tarim River,a total volume of 13.8×108m3 of water was delivered to the lower reaches from May 2000 to July 2003, in five times.Based on groundwater monitoring data before and after the fifth water transfer,this paper analyses the features of responses of groundwater table pre- and post-delivery of water to the lower reaches of the Tarim River.Before water transfer,the groundwater table was generally a horizontal line but after that,it presented a binary polynomial curve. The relationgship of ground-water table and distance from the river was thus expressed binary polynomial.Furthermore,the calculative formula of groundwater recharge volume was established by means of groundwater balance.The results of calculation showed that the average depth of groundwater has come back respectively from 9.0m to 3.0m and from 9.0m to 7.4m at Yingsu section and Yiganbujima section in the vicinities of the river(0~1000m).The total volume of groundwater recharged was 8.01×108m3 after the fifth water transpfer.All these can provide referenced index for the evaluation of benefits from water transfer.

Key words: intermittent water transfer, groundwater table, volume of groundwater recharge, lower reaches of the Tarim River

中图分类号: 

  • TV211